Lamelhuset/Baghuset, Stockholm, Sweden

  • Lamelhuset/Baghuset, Stockholm, Sweden
  • Lamelhuset/Baghuset, Stockholm, Sweden
  • Lamelhuset/Baghuset, Stockholm, Sweden
  • Lamelhuset/Baghuset, Stockholm, Sweden
  • Lamelhuset/Baghuset, Stockholm, Sweden
  • Lamelhuset/Baghuset, Stockholm, Sweden

Task: Erection of 160 tons of structural steelwork and 350 m2 of TRP metal sheet.
Client: SKANSKA AB/SKANSKA SA.
Time: 1st phase: November 2014, 2nd and 3rd phases: January-March 2016.

Site structural steelwork erection of 30Tons to 0,5Tons elements at level up to 19meters. Joint types: bolted and welded. Highly demanding task due to limitations arising from site being located in Central Stockholm and very limited time scale, imposing need to plan the job hour by hour. Erection has been completed in compliance with code EN 1090 requirements, Health and Safety strict rules and works schedule despite adverse weather conditions.