Task: Site fitting and welding of the bridge steel superstructure.
Client: SKANSKA.
Time: July – September 2016.
Pre-welding plates fitting and joints preparation by team of erectors. Site welding of steel plate box sections, suspension line eyes. S355 grade. Joints 100% UT/RT tested. Plates 16mm-40mm thick. Welding methods: 135 and 136. Man-hours: 3 000.